Blucher Design Proceedings
- Todas as edições
- Última edição
- Equipe de Produção
- ISSN 2318-6968
BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study
BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study
Silva, Isabella Rodrigues Oliveira da; Andrade, Max Lira Veras Xavier de
Conference full papers:
This paper shows the importance of implementing a BIM Execution Plan (BEP) as an instrument for the successfully BIM diffusion. BEP specifies the scope required for implementation, identifies processes, defines exchanges of information and describes needs of the project to provide adequate support for BIM implementation. The proposed BEP is to be implemented in the Design Sector (SINFRA) of a Brazilian Public University. It started with a diagnosis, choosing a pilot design project, defining the team to propose a BEP. This work presents the partial result of this BEP implementation, showing the benefits and the importance for the SINFRA.
This paper shows the importance of implementing a BIM Execution Plan (BEP) as an instrument for the successfully BIM diffusion. BEP specifies the scope required for implementation, identifies processes, defines exchanges of information and describes needs of the project to provide adequate support for BIM implementation. The proposed BEP is to be implemented in the Design Sector (SINFRA) of a Brazilian Public University. It started with a diagnosis, choosing a pilot design project, defining the team to propose a BEP. This work presents the partial result of this BEP implementation, showing the benefits and the importance for the SINFRA.
Palavras-chave:
DOI: 10.5151/sigradi2020-72
Referências bibliográficas
- [1] Brasil. Decreto nº Nº 10.306, de 2 de abril de 2020. Estabelece a utilização do Building Information Modelling - BIM ou Modelagem da Informação da Construção na execução direta ou indireta de obras e serviços de engenharia. Diário Oficial da União. Disponível em: http://www.planalto.gov.br/ccivil_03/_ato2019- 2022/2020/decreto/D10306.htm
- [2] Delatorre, V. Modelo conceitual que integra BIM nas fases iniciais do projeto arquitetônico: uma abordagem para o processo criativo e de ensino-aprendizagem. Florianópolis/SC. 2019. Disponível em: <https://core.ac.uk/download/pdf/30405331.pdf>.
- [3] Eastman, C. (2014) et al. Manual de BIM: um guia de modelagem da informação da construção para arquitetos, engenheiros, gerentes, construtores e incorporadores. Tradução: Cervantes Gonçalves Ayres Filho et al. Porto Alegre: Bookman.
- [4] Lacerda, D. (2013). Design Science Research: método de pesquisa para a engenharia de produção (pp. 741-761). Gest. Prod., São Carlos.
- [5] Leusin, S. (2018). Gerenciamento e Coordenação de Projetos BIM: Um guia de ferramentas e boas práticas para o sucesso de empreendimentos. 1. ed. Rio de Janeiro: Elsevier. ISBN 9788535290042.
- [6] Messner, J. et al. (2019). BIM Project Execution Planning Guide, Version 2.2. Computer Integrated Construction Research Program, The Pennsylvania State University,University Park, PA, USA, August, Disponível em: http://bim.psu.edu.
- [7] Robalo, A.; Silva, F.; Rodrigues, I.; Lança, L.; Chalaça, P. (2015). BIM Project Execution Plan: Concepção, desenvolvimento e construção de escola secundária. Departamento de Arquitectura, Lisboa. Disponível em: https://www.academia.edu/27959831/BIM_PROJECT_EXEC UTION_PLAN_BEP_-
- [8] _CONCEP%C3%87%C3%83O_DESENVOLVIMENTO_E_C ONSTRU%C3%87%C3%83O_DE_ESCOLA_SECUND%%81RIA.
- [9] Sacks, R.; Eastman, C.; Ghang, L.; Teicholz, P. BIM handbook: a guide to Building Information Modeling for owners, designeers, contractors, and facility mnagers. Third edition. Hoboken, New Jersey: Wiley, 2018.
- [10] Succar, B. (2008) Building information modeling framework: a research and delivery foundation for industry stakeholders. Automation in Construction. Disponível em: <www.elsevier.com/locate/autcon>.
- [11] Succar, B. (2018) BIM adoption policies insights from across the World. ÉTS, Montreal. Disponível em: <http://gridd.etsmtl.ca/publications/atelier-bimcompetitivite- construction-2018/Succar%20%20Macro%20BIM%20Adoption.pdf>.
Como citar:
Silva, Isabella Rodrigues Oliveira da; Andrade, Max Lira Veras Xavier de; "BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study", p-522-527.
In: Congreso SIGraDi 2020.
São Paulo: Blucher,
2020.
ISSN 23186968,
DOI 10.5151/sigradi2020-72
últimos 30 dias
183
downloads
407
visualizações
819
indexações
Sou autor desse trabalho
Você é citado neste trabalho?
Exportar citação - RefWork (RIS)
Copie a citação abaixo ou clique no botão Download para obter um arquivo com os dados
TY - CONF T1 - BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study JO - Blucher Design Proceedings VL - 8 IS - 4 SP - 522 EP - 527 PY - 2020 T2 - XXIV International Conference of the Iberoamerican Society of Digital Graphics AU - , SN - 23186968 DO - http://dx.doi.org/10.5151/sigradi2020-72 UR - www.proceedings.blucher.com.br/article-details/bim-project-execution-plan-for-infrastructure-superintendence-sinfra-of-the-federal-university-of-pernambuco-presentation-of-a-case-study-35480 KW - ER -
Exportar citação - BibTeX(BIB)
Copie a citação abaixo ou clique no botão Download para obter um arquivo com os dados
@article{Silva20144,
title="BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study",
journal="Blucher Design Proceedings",
volume="8",
number="4",
pages="522 - 527",
year="2020",
note="",
issn="23186968",
doi="http://dx.doi.org/10.5151/sigradi2020-72",
url="www.proceedings.blucher.com.br/article-details/bim-project-execution-plan-for-infrastructure-superintendence-sinfra-of-the-federal-university-of-pernambuco-presentation-of-a-case-study-35480",
author="Isabella Rodrigues Oliveira da Silva", "Max Lira Veras Xavier de Andrade",
keywords="",
}
Exportar citação - Text(TXT)
Copie a citação abaixo ou clique no botão Download para obter um arquivo com os dados
Isabella Rodrigues Oliveira da Silva, Max Lira Veras Xavier de Andrade, BIM Project Execution Plan for Infrastructure Superintendence (SINFRA) of the Federal University of Pernambuco: presentation of a case study, Blucher Design Proceedings, Volume 8, 2020, Pages 522-527, ISSN 23186968, http://dx.doi.org/10.5151/sigradi2020-72 (www.proceedings.blucher.com.br/article-details/bim-project-execution-plan-for-infrastructure-superintendence-sinfra-of-the-federal-university-of-pernambuco-presentation-of-a-case-study-35480) Palavras-chave:: ;